Delivery under PAC so far…

To date:

  • 376 new buildings
  • 167 refurbishments & alterations
  • 472 demolitions, with 97% re-use of materials

Key Milestones

Contract Award – 31 March 2006
Construction Start – March 2006
Service Commencement – July 2006
First Key Milestone – 2 RTR – 21 July 2007
Construction phase completed – 2014
Army Basing Programme contract variation – October 2016
End of contract – 2041

Independent Recognition

PPF Awards
  • Best Operational Defence Scheme
  • Best Government Agency Team award
  • Best Operational UK Project
  • British Safety Council Sword and Globe of Honour
    2011
  • Winner of the RoSPA Gold Award in 2014, 2015 and 2016
  • In 2015 winner of the Sanctuary Sustainability
    Project Award and the Sanctuary
    Sustainable Business Award
  • In 2015 received PSS Energy Award Commendation for Best Energy Management
Top